*****Please read before requesting an inspection*****
- Make sure item/work being requested to inspect is complete before the inspection date. This includes all required testing of systems or components that are applicable to the project.
- If the work or testing is not complete when the inspector arrives, it will be considered a fail, and you will need to request another inspection.
- No partial inspection approvals will be given.
- A 24hr notice is required for cancellations or a rescheduling.
UT Tyler Uniform General Conditions, Article 8. Quality Control
8.2.7 Covering Up Work
- If Contractor covers up any Work without providing Owner an opportunity to inspect, Contractor shall, if requested by ODR, uncover and recover the work at Contractor’s expense.
8.5 Inspection During Construction.
- 8.5.1 Contractor shall provide sufficient, safe, and proper facilities, including equipment as necessary for safe access, at all reasonable times for observation and/or inspection of the Work by Owner and its agents.
- 8.5.2 Contractor shall not cover up any Work with finishing materials or other building components prior to providing Owner and its agents an opportunity to perform an inspection of the Work.
- 8.5.2.1 Should corrections of the Work be required for approval, Contractor shall not over up corrected Work until Owner indicates approval.
- 8.5.2.2 Contractor shall provide notification of at least five (5) working days or otherwise as mutually agreed to ODR of the anticipated need for a cover-up inspection. Should ODR fail to make the necessary inspection within the agreed period, Contractor may proceed with cover-up Work but is not relieved of responsibility for Work to comply with requirements of the Contract Documents.